Date |
Action |
10/4/11 |
Application
packages become available. |
12/9/11 |
Application Review Workshop - Hourly - 10 am to 5 pm |
12/16/11 |
Project applications due by 5 p.m. |
2/3/12 |
District
notifies applicants of award status. District proceeds
with project negotiation and preparation of Financial Assistance
Agreements. |
5/4/12 |
District
and grantees begin to sign individual Financial Assistance Agreements. |
6/1/12 |
Projects
are implemented and reimbursements may begin. Quarterly reports
are due beginning 105 days after the agreement is returned to the recipient and every 90 days thereafter until the end of the project. |
Project
End |
A
final report is due for each project within 30 days of
project completion. Upon District approval of final report,
any remaining grant funds will be disbursed to the grantee. Grant recipients must retain records for
three years. |